Transneft Kama Region has completed the scheduled work on three trunk oil pipelines

Date of publication: 31 July 2017 Print

   Transneft Kama Region JSC has completed the scheduled work on three trunk oil pipelines.

   Thus, specialists of Tyngovatovo, Almetyevsk-Gorky-3 oil pumping station (PS) replaced sections of trunk oil process pipelines with total length of more than 600 meters. Four defects were removed from Almetyevsk — Aznakayevo-2 trunk oil pipeline by cutting of a spool. In addition, one defect was removed from Kaltasy — Kuibyshev within scheduled works, two stop valves were repaired.

   Crews of Almetievsk, Kazan, Udmurtia and Romashkino district oil pipeline departments of Transneft Kama Region participated in the repair works from 25 to 28 July of 2017.

   All work was done within the technical upgrade, revamping and overhaul program of Transneft Kama Region. The objective is to maintain trunk oil pipeline operation reliability. Oil transportation along oil trunk pipelines was resumed according to the schedule.