Transneft Kama Region continues constructing facilities as part of the project “Sever-25”

Date of publication: 15 May 2017 Print

   Transneft Kama Region continues works on construction of Mikhaylovka-1 petroleum products pump station (PPPS) in Chistopolsky District of the Republic of Tatarstan.

   Construction of the facility started in June 2016 as part of implementing the investment project “Sever-25”, providing for increasing petroleum products supplies to Primorsk port.

   Assembly of 4 main pump units, an electrical power equipment and electric lighting complex is conducted at the present time. Hydraulic tests of pipelines of a PIG trap are conducted.

   Works on assembling the fire-fighting system and testing the mud trap filters have been finished. The heating and ventilation systems of the fire-fighting pump station have been assembled; assembly of the roof and wall sandwich panels of the box for special vehicles parking has been finished.

   Commissioning of the facility is planned for 01 October 2017.

   The works are performed in accordance with the investment programme of Transneft Kama Region.